Concrete Bags from Volume and Bag Yield

Also known as how many bags of concrete · concrete mix bags

N=VyN = \frac{V}{y}
sig figs

Worked example: 12 ft3 of pour at 0.6 ft3 per bag → 20 bags. Press Try an example to run it live, then adjust anything.

Enter your known values, leave one input blank, and solves for the missing one. Tap a variable’s symbol to see what it means, with a typical value. Change any unit and the answer follows.

Where Concrete Bags from Volume and Bag Yield fits

In this toolkit
Learning zone

Concrete Bags from Volume and Bag Yield explained

VyN

Bagged concrete is bought by yield, not by weight, and the yield is printed on the bag: an 80 lb bag of standard premix makes about 0.60 ft³, a 60 lb bag about 0.45 ft³, a 30 kg Canadian bag about 13.5 L. Work out the volume of the pour, divide by the yield, and round up: a footing that comes up two inches short at the end of the day cannot be fixed with a second batch tomorrow.

The crossover point is worth knowing before you start hauling. One cubic yard is 27 ft³, which is 45 bags of 80 lb premix, over 1.5 tonnes of material and most of a morning in a mixer. Anything past roughly half a yard is usually cheaper and far easier as ready-mix delivered, even after the short-load fee. Bags earn their place on posts, small pads, repairs and anywhere a truck simply cannot reach.

Two things this number does not include: the extra for over-excavated footing bottoms and irregular formwork, which is what the separate waste allowance is for, and the water. Yield figures assume the bag is mixed to the specified water content, not soupy.

Concrete Bags from Volume and Bag Yield formula

N=VyN = \frac{V}{y}
Where
  • NN= Bags required
  • VV= Volume of the pour (ft³)
  • yy= Yield per bag (ft³)
Revised 16 October 2026