Levelized Cost of Energy (Annualized Capital plus Operating Cost over Annual Energy)

Also known as LCOE · levelized cost of electricity · levelised cost of energy · cost per megawatt-hour of a power plant · cost of electricity from a wind farm · cost of electricity from solar · capital recovery factor times capital plus O&M over energy · life cycle cost per kilowatt-hour · busbar cost of electricity · energy cost of a generator

LCOE=CRF Ccap+ComE\mathrm{LCOE} = \frac{\mathrm{CRF}\,C_{cap} + C_{om}}{E}
$
$
sig figs

Worked example: EIA onshore wind: capital 27.45 + fixed O&M 7.44 per MWh → 34.89. Press Try an example to run it live, then adjust anything.

Enter your known values, leave one input blank, and solves for the missing one. Tap a variable’s symbol to see what it means, with a typical value. Change any unit and the answer follows.

Learning zone

Levelized Cost of Energy (Annualized Capital plus Operating Cost over Annual Energy) explained

per yearCRF CcapComEper yearLCOEper unit of energy

The levelized cost of energy is the price per unit of energy at which a plant just covers everything it costs over its life. The numerator is the cost of one year: the capital cost CcapC_{cap}, turned into a level annual payment by multiplying it by the capital recovery factor CRF\mathrm{CRF}, plus the operating and maintenance cost ComC_{om} of a year. The denominator is the energy EE the plant delivers in that year, so the result is a cost per unit of energy, such as dollars per megawatt-hour, and different plants can be compared.

The formula is short because of an assumption: that the yearly energy and the yearly costs are level. Then the discounted lifetime cost over the discounted lifetime energy collapses to one line, and the capital recovery factor, found from the discount rate and the life, does the discounting. The page checks this by two routes: for 1 000 000 dollars of capital, 20 000 a year to run and 2 500 megawatt-hours a year over 30 years at 6.2 percent (a factor of 0.0742), the closed form and the discounted sums both give 37.68415 per megawatt-hour. Note where each input acts: the factor multiplies only the capital, so a capital-heavy plant feels the cost of money more than one whose cost is mostly running cost, and the energy divides everything, so a plant that produces less costs more for each unit.

The recovery period and the rate in the example come from the United States EIA, whose levelized costs for plants entering service in 2027 use a 30-year recovery period and a nominal after-tax weighted cost of capital of 6.2 percent; the method itself is the standard one of the NREL manual by Short, Packey and Holt (1995). The page's example uses the EIA's table 1a for onshore wind in 2021 dollars per megawatt-hour: levelized capital 27.45 plus fixed operating and maintenance 7.44, with no variable cost, is 34.89, before 2.91 for transmission. To enter those published components, the page takes one megawatt-hour with a recovery factor of 0.1, capital 274.5 and operating cost 7.44.

The simple form leaves things out. Fuel is not a separate term, so add its yearly cost to the operating cost. Taxes and subsidies, degradation of the output, and the cost of transmission and of the other plants needed to back up an intermittent one are not in it either. Use it to compare plants on one footing, not to price a contract.

Levelized Cost of Energy (Annualized Capital plus Operating Cost over Annual Energy) formula

LCOE=CRF Ccap+ComE\mathrm{LCOE} = \frac{\mathrm{CRF}\,C_{cap} + C_{om}}{E}
Where
  • LCOE\mathrm{LCOE}= Levelized cost of energy ($/MWh)
  • CRF\mathrm{CRF}= Capital recovery factor (/yr)
  • CcapC_{cap}= Capital cost ($)
  • ComC_{om}= Operating and maintenance cost per year ($)
  • EE= Energy produced in a year (MWh)
Where this comes from
  • Short, W., Packey, D. J., & Holt, T. (1995). A manual for the economic evaluation of energy efficiency and renewable energy technologies. NREL/TP-462-5173, National Renewable Energy Laboratory (US federal work; the standard manual for the levelized method with the capital recovery factor; the DOI record was checked in Crossref, the report was not opened here because the NREL and OSTI hosts could not be reached). Read it
  • U.S. Energy Information Administration, Levelized Costs of New Generation Resources in the Annual Energy Outlook 2022 (March 2022; US federal work, public domain), read 23 Oct 2026: all levelized costs use a 30-year cost recovery period and a nominal after-tax weighted average cost of capital of 6.2 percent for plants entering service in 2027; Table 1a splits the 2027 cost of onshore wind (capacity factor 43 percent) into levelized capital $27.45, fixed O&M $7.44, variable $0.00 and transmission $2.91, a total of $37.80 per megawatt-hour in 2021 dollars. Read it