Reorder Point
Also known as ROP · order point · when to reorder · reorder level · demand during lead time · trigger quantity
Worked example: 120 a day over a 10-day lead time → reorder at 1,200. Press Try an example to run it live, then adjust anything.
Enter your known values, leave one input blank, and solves for the missing one. Tap a variable’s symbol to see what it means, with a typical value. Change any unit and the answer follows.
Where Reorder Point fits
- Inventory control5 formulas
See also
Safety Stock (Statistical Buffer): Add safety stock to this figure when demand or lead time is uncertain.Economic Order Quantity (Wilson EOQ): The reorder point says when to order; EOQ says how much.Reorder Point explained
The reorder point answers "when", where EOQ answers "how much". If you use 120 units a day and the supplier takes ten days from purchase order to receiving dock, you will consume 1,200 units while waiting. Trigger the order when the shelf hits 1,200 and the last unit walks out the door as the truck backs in.
Two errors turn up constantly. The first is mixing periods: a weekly usage rate against a lead time in days will be off by a factor of seven, and the answer looks plausible enough to survive a meeting. The second is using the supplier's promised lead time rather than the one you have actually measured. Quoted lead time is a sales figure. Pull the last twenty receipts, take the real average, and use that.
Note what this version deliberately leaves out. Pure assumes demand and lead time are both known exactly, which they never are, so a reorder point built this way stocks out roughly half the time by construction. Add safety stock on top before you rely on it.
Reorder Point formula
- = Reorder point (units)
- = Demand per day (units/day)
- = Lead time (d)