Standard Time from a Time Study

Also known as standard time · normal time · allowance factor · performance rating · time study · work measurement · allowed time per piece

Ts=To R (1+A)T_s = T_o\,R\,(1 + A)
sig figs

Worked example: 2.00 min observed, rated 110%, 15% allowance → 2.53 min. Press Try an example to run it live, then adjust anything.

Enter your known values, leave one input blank, and solves for the missing one. Tap a variable’s symbol to see what it means, with a typical value. Change any unit and the answer follows.

Where Standard Time from a Time Study fits

In this toolkit

See also

Wright's Learning Curve (Unit Time): Time study measures a settled operation; the learning curve describes one that is still improving.Takt Time: Standard times are the task times you balance against takt.
Learning zone

Standard Time from a Time Study explained

ToRATs

A stopwatch reading is not a standard. Two things have to happen to it first. Rate the operator against normal pace, because the person you timed may have been working at 110% or at 85%, and multiply. Then add an allowance for rest, personal needs and unavoidable delay, because nobody works 480 minutes out of an 8-hour shift. Two minutes observed, rated at 110%, with a 15% allowance, gives 2.00×1.10×1.15=2.532.00 \times 1.10 \times 1.15 = 2.53 minutes allowed.

Performance rating is the soft joint in an otherwise hard method, and it is why time study is contentious. It is a trained human judgement, calibrated against films of "normal" pace such as dealing a deck of cards in 0.50 minutes, and two rated observers can differ by five points on the same operator. That variation flows straight through to the standard, and from there into piece rates and costings.

Watch the allowance convention. Most North American practice applies the allowance to the normal time as written here, so 15% adds 15% of 2.20 minutes. Some texts, and some union agreements, express the allowance as a fraction of the total shift instead, in which case the multiplier is 1/(1−A)1/(1-A) and 15% becomes a 17.6% addition. The two differ by enough to matter on an incentive rate, and the contract usually specifies which one applies.

Standard Time from a Time Study formula

Ts=To R (1+A)T_s = T_o\,R\,(1 + A)
Where
  • TsT_s= Standard time (min)
  • ToT_o= Observed time (min)
  • RR= Performance rating
  • AA= Allowance fraction
Revised 19 September 2026
Cite this page

formula.expert. (2026, September 19). Standard Time from a Time Study Formula & Calculator. https://formula.expert/solvers/standard-time-allowance