Practice problems
Answer key at the back. Work in the units each problem states.
Grades, Slopes & Earthwork
1. Percent grade, three ways — An as-built check on a parking-lot cross fall: the level run between the two spot heights is 150 m, and the surface falls 3 m across it. Calculate the percent grade the contractor actually built.
2. Percent grade, three ways — A ramp is to be built at a uniform 2.5 % over a level run of 80 m, and the fabricator needs the total vertical before ordering the handrail. Determine the vertical rise over that run.
3. Elevation on the grade — A gravity sewer leaves a benchmark at EL 220.35 m and runs 180 m of level chainage at a uniform -1.00 %. The minus sign on the drawing is the designer's, not a typing error. Determine the elevation at the far end of that run.
4. Elevation on the grade — An as-built survey returns two reduced levels on the same pipe run: EL 214.60 m at the upstream manhole and EL 211.60 m at the downstream one, 150 m of level chainage apart. Determine the grade the pipe was actually laid at.
5. Earthwork volumes — Two cross sections are taken through a road cutting, 60 m of chainage apart. The first plots 18 m² of cut, the second 30 m², and no section was taken between them. Calculate the volume of cut between the two sections.
6. Earthwork volumes — A borrow area is surveyed at three sections spanning 50 m end to end: 24 m² at the near end, 33 m² at the midpoint, and 36 m² at the far end. The specification calls for the prismoidal computation, not the end-area one. Calculate the volume between the end sections.
7. Swell and shrink — A survey puts 1500 m³ of common earth in the cut, measured in place. The soils report gives the material 20 % swell, and the haulage contractor is paid by the box. Determine the volume that cut becomes once it is loaded.
8. Swell and shrink — Weighbridge and box counts say 1300 m³ of loose material left the site. The soils report gives the material 30 % swell, and the quantity surveyor pays for excavation in place. Determine the volume that was removed from the ground.
9. Ordering the material — A slab 12 m by 4 m is to be poured 200 mm thick. The site allows 10 % for waste, over-dig and the truck's last wash-out. Calculate the volume of concrete to order.
10. Ordering the material — A car park of 800 m² is to receive a single compacted wearing course 60 mm thick. The mix's compacted density is 2350 kg/m³, and the plant sells by the tonne. Calculate the tonnage of mix to order.
11. The Cut Sheet — Last sheet of the day. A road cut runs from ch 0+000, where the design invert sits at EL 150.00 m, to ch 0+250, and the invert falls 5.00 m over that 250 m of level chainage. The cross sections plot 8 m² of cut at the first station and 16 m² at the last, with no section between. The soils report gives the material 20 % swell, and each haul truck carries 10 m³. No calculator tonight — every number here divides in your head. Work each line; every answer feeds the next. Determine how many truckloads the cut will take, one line at a time.
12. The Cut Sheet — Bonus mark, on the way out. The same cut holds 2400 m³ measured in place, and the material swells 25 %. The haulage contractor offers 7 trucks, each good for 20 trips a day at 20 m³ a load. The foreman has already looked at the survey figure and said it will be a one-day job. Determine whether that fleet clears the cut in the day.
Curves, Traverse & Levelling
13. Horizontal curve geometry — A rural highway alignment is drawn with a 8° curve on the arc definition — the sheet gives the degree of curve and nothing else about the circle. Stations run in 100 ft units throughout. Determine the radius of the curve.
14. Horizontal curve geometry — Two straights on a haul-road alignment meet at a corner, deflecting through Δ = 50°. The designer has fitted a circular curve of radius 800 ft into the corner. The crew needs to know how far back from the corner to set the point of curvature. Determine the tangent length of the curve.
15. Chords and offsets — A 500 m radius curve carries a plant access road through a deflection of Δ = 40°. The crew cannot chain the arc — the ground inside the bend is a stockpile — so they intend to set the two ends and measure straight between them as a check. Determine the long chord of the curve.
16. Chords and offsets — A 300 m radius curve turns a haul road through Δ = 40°. A concrete headwall sits at the corner where the two straights would have met, and the designer needs to know how much room the curve actually leaves between that corner and the road. Determine the external distance of the curve.
17. Vertical curves — A road profile runs at 1 % and must leave at -2 %, so the two tangents meet in a crest. The design speed table gives K = 30 m per percent of grade change for this class of road. Determine the length of vertical curve the standard requires.
18. Vertical curves — An equal-tangent parabolic vertical curve is 300 m long. It begins at the BVC at elevation 120.00 m with the profile running at g₁ = -6 %, and the algebraic grade change through the curve is A = 12 %. A drainage structure is proposed 100 m past the BVC. Determine the finished road elevation at that station.
19. Sight distance and speed — A site haul road is being posted at 90 km/h. The standard allows 2.5 s of perception-and-reaction time and a deceleration of 3.4 m/s² on a wet surface. Calculate the stopping sight distance the road must provide.
20. Sight distance and speed — A crest on an access road joins two grades whose algebraic change is A = 8 %. The standard calls for 250 m of sight distance at that design speed, using the metric AASHTO heights: a driver's eye at 1.08 m and an object 0.60 m tall. The sight distance is shorter than the curve. Determine the crest curve length that delivers that sight distance.
21. The traverse — A crew occupies station B on a closed traverse. The course they have just run in, from A to B, was recorded at an azimuth of 336° from north. They must now sight back to A to orient the instrument. Determine the azimuth they set to look back down that course.
22. The traverse — A closed traverse round a proposed lagoon has one course of 120.00 m run at an azimuth of 300° from north. The field book is being reduced to northings and eastings before the parcel can be plotted. Determine the latitude of that course, signed.
23. Level runs and stadia — A level run leaves a benchmark at elevation 85.00 m. With the instrument set between the benchmark and the first turning point, the rod on the benchmark reads 3.10 m and the rod on the turning point reads 1.50 m. Determine the elevation of the turning point.
24. Level runs and stadia — An older external-focusing instrument is sighted on a level staff. The lower stadia hair cuts the staff at 1.200 m and the upper hair at 2.440 m. The instrument's stadia interval factor is K = 100 and its additive constant is C = 0.30 m. The sight is horizontal. Determine the horizontal distance to the staff.
25. Closing the Loop — A three-course closed traverse round a settling cell. Course 1 runs A to B, 500.00 m at azimuth 53.13° — take cos 53.13° as 0.600 and sin 53.13° as 0.800 exactly. Course 2 runs B to C, 300.12 m due south. Course 3 runs C back to A, 399.84 m due west. No calculator. Determine the sum of the departures round the whole loop.
26. Closing the Loop — The same loop, now on the latitude side. Course 1 is 500.00 m at azimuth 53.13°, with cos 53.13° = 0.600. Course 2 is 300.12 m due south. Course 3 is 399.84 m due west, and it contributes no latitude at all. The three courses total 1,200 m to the nearest metre, and the departures were found to sum to +0.16 m. Boundary work on this job is specified at 1:5,000. No calculator. Work the latitudes down to the closure, the precision ratio, and the call on the crew's day.
Stacks & Plumes
27. Lapse and pressure — A met mast beside a chemical works reads 20 °C at ground level and 13.5 °C at 1000 m on the same pass. The dispersion sheet wants the profile as a rate. Determine the environmental lapse rate, in C° per kilometre.
28. Lapse and pressure — A dispersion model needs the ambient pressure at a plant sitting 1500 m above the coastal station that reports for it. The station reads 101.325 kPa, and the layer between them is taken as isothermal at 10 °C. Calculate the pressure at the plant.
29. Wind aloft — The anemometer on the works gatehouse stands at the standard 10 m and averages 6 m/s. The stack top is 40 m above the same ground, and the terrain around it is the suburb the works sits in, for which the table gives a profile exponent of p = 0.25. Determine the wind speed at the stack top.
30. Wind aloft — A tall met mast beside the works carries anemometers at 10 m and 100 m. Over an hour of steady wind they average 3 m/s and 6 m/s. The modeller wants the site's own profile exponent rather than a table value. Determine the power-law exponent the site is showing.
31. The stack itself — A stack test measures 20 m³/s of flue gas at stack conditions leaving a round stack of 1600 mm inside diameter. Calculate the exit velocity.
32. The stack itself — A tall flue serving a low-temperature economiser stands 40 m tall with no fan on it. Outside air is 1.2 kg/m³ and the flue gas inside is 0.8 kg/m³. (g = 9.81 m/s²) Calculate the theoretical draft the flue develops.
33. Plume rise — A stack of 2 m inside diameter discharges at 20 m/s. The flue gas is at 400 K and the ambient air at 280 K. (g = 9.81 m/s²) Calculate the buoyancy flux parameter for that plume.
34. Plume rise — A 30 m stack has a calculated buoyancy flux of F = 27 m⁴/s³. The afternoon is neutral, the wind at stack top is 4 m/s, and the assessment point is 512 m downwind. Determine the plume rise there, and the effective stack height it gives.
35. Emission bookkeeping — The analyser reads 50 ppm of nitric oxide on a dry basis, and the permit limit for it is written in mg/m³ at 25 °C and 101.325 kPa. The molar mass of nitric oxide is 30.01 g/mol. Convert the reading to a mass concentration.
36. Emission bookkeeping — A stack test on a boiler running with the damper wide open reads 150 ppm of NOx with 10 % oxygen in the same dry sample. The permit is written at 3 % reference oxygen. Restate the reading at the reference oxygen.
37. The Gaussian plume — The hour is classified Pasquill F — stable, a clear and nearly calm night. For the vertical spread the table gives a = 0.062 and b = 0.7, and the receptor of interest is 2000 m downwind. Determine the vertical dispersion coefficient at that distance.
38. The Gaussian plume — A source emitting 50 g/s disperses from an effective height of 120 m into a 4 m/s wind. At the receptor the spreads are σ_y = 150 m and σ_z = 60 m, and the ground under the plume is flat and fully reflecting. Calculate the ground-level concentration on the plume centreline.
39. Capture and compliance — Simultaneous inlet and outlet trains on a high-efficiency cyclone on a hammer mill report 10000 mg/m³ entering and 200 mg/m³ leaving, both on the same dry basis. Determine the collection efficiency of the device.
40. Capture and compliance — A high-efficiency cyclone on a hammer mill is guaranteed at 98 % collection efficiency, and the inlet loading is measured at 10000 mg/m³. Determine the outlet loading the guarantee implies.
41. The Stack Test — Exam-hall rules, and the last question on the paper. A foundry's cupola stack on a cold morning is 40 m tall with a 2 m inside bore — take the bore area as 3.14 m². The test crew measures 62.8 m³/s of flue gas at 400 K into ambient air at 272 K, emitting 50 g/s of the pollutant. The wind at stack top is 4 m/s, the hour is neutral, and the nearest residence is 1000 m directly downwind, where the sheet gives σ_y = 200 m and σ_z = 100 m and has pre-multiplied π·σ_y·σ_z·u = 2.5 × 10⁵ m³/s. Tonight g = 10 m/s², and e⁻² = 0.135. The ambient limit at the residence is 20 µg/m³. Work the source from the stack exit to the fenceline, and say whether it complies.
Noise on Site
42. Adding noise — Two items of plant stand side by side on a slab. Running alone, the first gives 86 dBA at the operator's position and the second gives 80 dBA at the same spot. Calculate the level at that position with both machines running.
43. Adding noise — A survey takes each source in turn from one microphone position on the site boundary: the generator alone reads 86 dBA there, and the compressor alone reads 80 dBA. Determine the boundary level with both running together.
44. Distance attenuation — A single vibratory roller on open ground reads 100 dBA at 2 m. The site is flat, hard and free of anything to reflect off, so the machine behaves as a point source radiating into the open. Calculate the level at 20 m from the same machine.
45. Distance attenuation — A generator set is rated at a sound power level of 98 dB re 1 pW. It stands on the concrete apron, so the directivity factor is Q = 2, and a labourer works 2 m away. Determine the sound pressure level at the labourer's position.
46. Rooms that ring — A plant room of 1500 m³ has been surveyed surface by surface, and the total absorption comes to 100 m² sabins. The room is hard and lightly treated, so Sabine's assumption of an evenly diffuse field holds well enough. Calculate the reverberation time of the room.
47. Rooms that ring — A control room is taken off surface by surface at 500 Hz: 150 m² of absorptive ceiling tile at α = 0.65, 300 m² of painted block wall at α = 0.06, and 150 m² of sealed concrete floor at α = 0.03. Calculate the total absorption of the room.
48. Walls that block — A partition between a plant room and an office is tested in a laboratory. The intensity striking the plant-room face is 1 × 10⁻² W/m², and the intensity radiated from the office face is 1 × 10⁻⁸ W/m². Calculate the transmission loss of the partition.
49. Walls that block — A screening panel weighs 10 kg per square metre of face. The plant it is screening puts most of its energy into the 1000 Hz octave band, and no laboratory test of this build exists. Determine the transmission loss the mass law predicts in that band.
50. Hearing safety — A dosimeter on a fitter's collar reads a steady 100 dBA while he works beside the screening plant. The jurisdiction sets an 85 dBA criterion on a 3 dB exchange. Calculate the time he may be exposed to that level in one day.
51. Hearing safety — A method statement allocates a thirty-minute entry to change a screen deck — 0.5 h at one position — and the whole of that worker's daily noise budget goes to it. The site runs to 85 dBA as its criterion with a 3 dB exchange rate. Determine the highest steady level the position may run at.
52. The Noise Survey — Two identical generator sets, each rated 99 dB re 1 pW, sit on the hard yard slab, so Q = 2 for each. A banksman works 4 m from the pair for a 6 h stint. The site runs to an 85 dBA criterion on a 3 dB exchange. Tonight: the 1 m spreading term on hard ground is exactly −8 dB, and every doubling of distance costs exactly 6 dB. Determine whether that stint is permitted.
53. The Noise Survey — A single generator set rated 105 dB re 1 pW stands on the yard slab, Q = 2. The site wants an outdoor work station where a labourer can work a full 8 h shift without hearing protection, against an 85 dBA criterion on a 3 dB exchange. The station is currently pegged out at 3 m. Tonight: the 1 m spreading term on hard ground is exactly −8 dB, and every doubling of distance costs exactly 6 dB. Determine whether the pegged position will do.
Water on the Land
54. Water in the soil — A soil survey describes the field as a coarse sand: field capacity 12% by volume, permanent wilting point 5% by volume. The crop in it is rooted to 100 cm. Calculate the available water capacity of that root zone.
55. Water in the soil — The root zone under a mid-season maize crop holds 150 mm of available water. The scheduling plan for the season works to a management allowable depletion of 50%. Determine the depth of water the crop may draw before the next irrigation is due.
56. Crop thirst — The weather station beside the field reports a reference evapotranspiration of 4 mm/day for a clipped grass surface. The crop coefficient table gives K_c = 1.2 for this crop at this growth stage — a full mid-season canopy in a dry, breezy climate. Calculate the water this crop is using per day.
57. Crop thirst — A scheduling sheet gives the root zone 81 mm of readily available water. Through the current stretch of weather the crop is using 9 mm/day, and no rain is forecast. Calculate how long the crop can go before the next irrigation is due.
58. Net and gross — Over a month the crop used 180 mm of water. 90 mm of rain fell in that month, but the record notes that only 60 mm of it was effective — the rest ran off the headland or drained past the roots within the day. Calculate the depth irrigation had to supply over that month.
59. Net and gross — The root zone needs 30 mm of water stored in it. The field is watered by a wheel-line sprinkler set on a windy bench, and a catch-can evaluation put the application efficiency at 60% — the rest goes to wind drift, runoff and drainage past the roots. Determine the gross depth that must be applied to store that much.
60. Running the set — A sprinkler set covers 3 ha and is fed 40 L/s from the mainline. The schedule calls for 24 mm of water to go on that set. Calculate how long the set must run.
61. Running the set — A new system is being sized for 36 ha. Peak crop water use in the hottest fortnight is 8 mm/day, the design application efficiency is 80%, and the plan is to run the system 20 hours a day, leaving the rest for moves and breakdowns. Determine the flow the system must be able to deliver.
62. Calibrating the sprayer — A boom sprayer is calibrated in the yard. One nozzle, caught in a jug for a timed minute, delivers 0.5 L/min. The nozzles sit at 0.5 m along the boom, and the tractor's measured ground speed in the field is 6 km/h. Calculate the volume the boom is applying per hectare.
63. Calibrating the sprayer — A nozzle catalogue quotes 1 L/min at a rated pressure of 400 kPa. The boom on this machine actually runs at 225 kPa. Determine the output that nozzle really gives at the working pressure.
64. Tank mixing — A sprayer carries a 600 L tank and is calibrated to apply 100 L/ha. Calculate the ground one full tank will treat.
65. Tank mixing — A 60 ha field is to be sprayed at 100 L/ha from a sprayer with a 800 L tank. The water point is at the yard, twenty minutes away, and the operator wants to know before starting how many times the machine comes home. Determine how many tank loads the field will take, and how many fills that means.
66. Seeds and stands — A seed tag on a bag of forage reads: purity 90%, germination 95%. The bag is priced by weight, and the buyer wants to know what share of that weight is worth paying for. Calculate the pure live seed in the bag.
67. Seeds and stands — A planter is set for 100 cm rows and drops a seed every 20 cm along the row. Every seed is assumed to make a plant for this calculation. Calculate the plant population that geometry gives.
68. Field work rates — A mounted rotary mower works 9 m wide at 8 km/h. Turning at the headland, filling, and unblocking together cost enough time that the field efficiency for this job is 75%. Calculate the effective field capacity of that outfit.
69. Field work rates — A machine 18 m wide travelled at 8 km/h all day. The field record shows it actually covered 10.8 ha in each hour it was in the field. Determine the field efficiency the day returned.
70. The Irrigation Day — A dry week, and one field to schedule. The soil survey gives field capacity 28% by volume and permanent wilting point 18%; the crop is rooted to 120 cm. The plan works to a management allowable depletion of 50%. The weather station reports reference evapotranspiration of 4 mm/day, and the crop coefficient table gives K_c = 1.5 for this stage. No rain is forecast. Work the schedule down from the soil: reserve, allowance, crop use, and the days between irrigations.
71. The Irrigation Day — Same field, and the pump end of the same decision. The root zone needs 45 mm stored, and the sprinkler block's application efficiency is 75%. The set covers 5 ha and the mainline delivers 500 m³/h. The block must be moved for the next set in 8 hours. (Tonight: 1 mm over 1 ha is 10 m³, exactly.) Work the set down from the depth: gross depth, volume, run time, and whether the block clears its window.
Navigation & Field Craft
72. Map and pace — A survey team plots a leg between two trig points on a 1:25,000 Explorer sheet. The ruler laid along the leg reads 8.0 cm. Calculate the real distance that leg represents, in kilometres.
73. Map and pace — A technician walks a pipeline offset with no GPS lock. Her calibration walk over a taped 100 m puts her pace at 0.75 m, and she counts 200 paces from the marker post to the valve box. Calculate the distance from the post to the valve box.
74. Slope distance and height — A route card leg runs 1120 m on the map and crosses 150 m of contour, climbing steadily the whole way. Determine the distance actually walked on the ground.
75. Slope distance and height — A forestry crew must clear a white spruce away from a new service corridor. The technician paces 30 m out on level ground, sights the crown, and the clinometer reads 35° above horizontal. Her eye stands 1.6 m off the ground. Calculate the height of the tree.
76. Time on the trail — A survey crew books a day on a moorland traverse — 15 km measured off the sheet, 900 m of climb totalled from the contours, no scrambling anywhere on it. Determine the planning time Naismith's rule gives.
77. Time on the trail — A crew times itself over the first hour of a long moorland leg and finds it is making good 4.5 km/h across the ground, tussocks and all. From the checkpoint they have reached, 9 km of similar ground remains. Determine the time still to run at that rate.
78. Bearings and the needle — A survey party runs a leg from station A to station B on a forward azimuth of 72°. Determine the back azimuth of that line.
79. Bearings and the needle — A workboat runs a survey line with the ship's compass reading 285°. The deviation card for that heading gives 3° E, and the chart's compass rose gives the local variation as 8° E. Determine the true heading to plot on the chart.
80. The great circle — A cable survey is being priced between London (51.51°, -0.13°) and New York (40.71°, -74.01°), north and east taken as positive. The earth is treated as a sphere of mean radius 6,371 km. Calculate the great circle distance between the two positions.
81. The great circle — A ferry operator plans a great circle track from London (51.51°, -0.13°) to New York (40.71°, -74.01°), north and east positive. Determine the initial true bearing of the great circle track.
82. Dead reckoning — A survey launch leaves a fixed mark and holds a true course of 240° for 4 hours at 8 knots over the ground, with no fix available in between. Determine the change of latitude over that run, in minutes of arc.
83. Dead reckoning — After 6 hours running on dead reckoning, a vessel takes a fix. The fix lies 9 nautical miles north and 12 nautical miles east of the DR position. Determine the drift — the speed of the current that carried her there.
84. The wind triangle — A light aircraft holds 90 knots true airspeed on a ferry leg. The wind at cruise is 25 knots, 60° off the intended track. Calculate the speed the aircraft is making good over the ground.
85. The wind triangle — A pilot intends to hold a track across an open bay at 120 knots true airspeed. The wind is 30 knots from 45° off that track. Determine the wind correction angle — how far off track to point the nose.
86. Horizon and clock — A radio survey puts an antenna platform 4 m above mean sea level, and the question is how far the sea horizon stands from it. Take the earth as a sphere of radius 6,371 km. Calculate the geometric distance to the horizon.
87. Horizon and clock — Two field camps sit on the same parallel, 22.5° of longitude apart, the second one east of the first. Determine how much earlier the sun crosses the eastern camp's meridian.
88. The Field Exercise — Field exercise, 1:50,000 sheet, no calculator and no GPS. From the road head the party walks the first leg on a bearing of 143°, counting 800 paces; this walker's calibration walk puts her pace at 0.75 m. From the turning point the route card's second leg measures 5.8 cm along the ruler on the sheet. The last 2400 m of that second leg climbs 700 m of contour. The party then returns to the road head down the same line it came out on. Naismith at 5 km/h and 600 m/h; the ground is good. Work the route card end to end — the legs, the climb, the time, and the bearing home.
89. The Field Exercise — Field exercise, 1:50,000 sheet, no calculator and no GPS. From the road head the party walks the first leg on a bearing of 143°, counting 800 paces; this walker's calibration walk puts her pace at 0.75 m. From the turning point the route card's second leg measures 5.8 cm along the ruler on the sheet. The last 2400 m of that second leg climbs 700 m of contour. The party then returns to the road head down the same line it came out on. Naismith at 5 km/h and 600 m/h; the ground is good. Work the route card end to end — the legs, the climb, the time, and the bearing home.
Engineering Economics
90. Single payments — A renewal fund holds $10,000 today and is credited 10% at the end of every year. The board will not start the works until the fund reaches $16,105.1, and nothing further will be paid in. Determine how many years the fund needs.
91. Single payments — A renewal fund holds $25,000 today and is credited 5% at the end of every year. The board will not start the works until the fund reaches $36,936.39, and nothing further will be paid in. Determine how many years the fund needs.
92. Honest rates — An equipment finance house quotes 24% a year on a chlorination skid, compounded monthly — that is 12 compounding periods in the year. Determine the effective annual rate the plant will actually pay.
93. Honest rates — A municipal reserve fund earned 9% over the year. Over the same year the construction price index the fund exists to keep up with rose 3%. Determine the real rate the fund earned.
94. Uniform series — A water district opens a replacement reserve for its high-lift pumps and pays $12,000 into it at the end of every year for 15 years. The reserve is credited 8% a year. Calculate what the reserve holds at the end of the term.
95. Uniform series — An automated coagulant dosing upgrade costs $80,000 to install and is forecast to save $15,000 a year in chemical for 12 years. Capital is discounted at 8%. Calculate the net present value of the upgrade.
96. Capital recovery — A 20-year service life is assumed for a new sludge pump, and the utility's cost of capital is 6%. The lifecycle sheet wants every capital cost converted to an annual charge before it is compared with running costs. Determine the capital recovery factor for that life and rate.
97. Capital recovery — A contractor finances a $120,000 vacuum truck over 84 monthly payments. The finance house charges 5.4% a year nominal, which is 0.45% a month. Determine the level monthly payment.
98. Comparing alternatives — A duty–standby dosing station costs $60,000 installed, lasts 15 years, and costs $9,000 a year to run. Capital is charged at 6%. Calculate the equivalent annual cost of owning and running it.
99. Comparing alternatives — Two machines are tendered for the same duty. Pump A costs $40,000, lasts 15 years and costs $6,000 a year to run. Pump B costs $25,000, lasts 8 years and costs $8,000 a year to run. Either will be replaced with its own kind at the end of its life. Capital is charged at 8%. Determine which machine the plant should buy.
100. Payback and return — A capital committee will approve a $35,000 variable-speed retrofit only if it pays for itself within 2.5 years. The energy team must now show what the drives have to deliver. Determine the annual saving the retrofit must achieve.
101. Payback and return — A rental fleet of dewatering pumps cost $15,000 to buy and refurbish. Over the contract it returned $24,000 in hire income and residual value, all in. Determine the return on investment.
102. Wearing out on paper — A packaged pressure filter was bought for $85,000. The asset register gives it a 15-year life and expects it to be worth $10,000 at the end of it. The books use straight-line depreciation. Calculate the annual depreciation charge.
103. Wearing out on paper — A mobile dewatering trailer cost $120,000 new and is written down at 25% of its remaining book value every year. 2 years have now passed. Calculate the current book value.
104. The Tender — Last page of the tender evaluation. Two bids for the same booster station, both with a 15-year life, both discounted at 10%. Bid A: $300,000 installed, $35,000 a year to run, and a $100,000 rebuild due in year 5. Bid B: $200,000 installed, $60,000 a year to run, no rebuild. Tonight (P/F, 10%, 5) is 0.6 and (A/P, 10%, 15) is 0.13 — no calculator. Work each line; every answer feeds the next. Determine which bid to recommend, one line at a time.
105. The Tender — Bonus mark, on the way out. The winning station goes on the asset register at its $180,000 installed cost, with a $30,000 residual expected after 10 years, written down straight line. Determine the annual depreciation charge for the books.